Risk Mapping and Risk Types
Map each risk to the activities and cost elements it would hit, choose how its impact applies, and model risk types a register alone cannot hold.
How It Works
Quantify
On the Risks tab, switch on editing and give the risk a probability and a schedule and cost impact in any of the ten distributions.
Map
Link it to one or more activities or cost elements. Impacts can be absolute or relative to the activity’s duration.
Choose How It Applies
Spread one impact across the mapped activities or apply it to each, or let each activity draw its own impact.
Pick a Risk Type
Discrete, non-existence, recurring (binomial) and calendar risks, with pre- and post-mitigation positions.
Details
What You Get
- Risks on the same activity combine in series or in parallel.
- A non-existence risk removes an activity or its duration.
- A recurring risk occurs once or several times, drawn from a binomial.
- An alternate position blends pre and post by the chance the action is carried out and the chance it works.
- AI suggests mappings from the risk text and the schedule.
- Import and export risks and mappings as Excel workbooks.
Limits and Conditions
- Recurring risks use a binomial count. A Poisson count is not available.
Related Features
- QRA Engine
Ten Distributions
Describe each uncertain duration, impact or cost with one of ten distributions, and see its shape as you enter it.
- Workspace
Actions and Mitigation
Actions with owners, dates and status on each risk, and the effect each action has in the Monte Carlo model.
- QRA Engine
Correlation
Tell the model which risks and costs move together, check that the matrix is valid, and see the correlation the run achieved.
- QRA Engine
Calendar Risks and Weather
Model downtime as a calendar: a seasonal shutdown, recurring events, a daily chance, or downtime built from historical weather at the site.